Mark as Completed

When a REDCap project is marked as ‘Completed’, the study team will not have access to the project data or features at all - the project is made completely inaccessible.

A REDCap administrator can move the project back to an accessible status in the future.

 

Mark Project as Completed

  1. Go to the Project Setup page

  2. Click the ‘Other Functionality’ tab

  3. Click ‘Mark project as Completed'

 

Find Completed Projects

Study team members should be able to see their ‘Completed Projects’ on the ‘My Projects’ page when the following option is selected: